Stakeholder engagement plan

The actions, owners and dates for moving named stakeholders from their current engagement level to the level the work requires.

An engagement plan exists to close gaps, so it is only as good as the assessment that produced them: a stakeholder already at the level the work needs belongs in no plan at all. The useful form names an owner and a date per gap rather than listing communication channels, because a channel is not an action and nobody is accountable for a newsletter. Plans decay quickly, since the positions they were built against drift with reorganisations, budget rounds and changes of leadership, which is why the assessment behind the plan is re-run at stage gates rather than filed at initiation.