Mastering Earned Value Management: A Comprehensive Guide to EV, PV, and AC

Mastering Earned Value Management: EV, PV, AC Explained

Earned Value Management: Unlocking Project Success with EV, PV, and AC

Dive into the world of Earned Value Management (EVM) and uncover the power of Earned Value (EV), Planned Value (PV), and Actual Cost (AC). Learn how these metrics can revolutionize your project management approach and drive project success.

Understanding Earned Value Management (EVM)

Earned Value Management (EVM) is a powerful project management technique that integrates scope, schedule, and cost data to provide a comprehensive view of project performance. At its core, EVM relies on three key metrics: Earned Value (EV), Planned Value (PV), and Actual Cost (AC).

The Three Pillars of EVM: EV, PV, and AC

Planned Value (PV)

Planned Value, also known as Budgeted Cost of Work Scheduled (BCWS), represents the authorized budget for the work scheduled to be completed by a specific date. It answers the question: "How much work should have been done by now?"

Example:

Let's say you're managing a software development project with a total budget of $100,000 and a duration of 10 months. After 3 months, you expect 30% of the work to be completed.

PV = Total Budget * Planned % Complete

PV = $100,000 * 30% = $30,000

This means that after 3 months, you should have completed $30,000 worth of work according to your plan.

Earned Value (EV)

Earned Value, or Budgeted Cost of Work Performed (BCWP), is the value of work actually completed at a given point in time. It addresses the question: "How much work has actually been accomplished?"

Example:

Continuing with our software project, let's say that after 3 months, your team has actually completed 25% of the work.

EV = Total Budget * Actual % Complete

EV = $100,000 * 25% = $25,000

This indicates that $25,000 worth of work has been completed, which is less than planned.

Actual Cost (AC)

Actual Cost, also referred to as Actual Cost of Work Performed (ACWP), represents the total costs incurred in accomplishing the work completed up to a specific date. It answers: "How much have we spent so far?"

Example:

In our software project, let's say that after 3 months, you've spent $28,000 on labor, materials, and other expenses.

AC = $28,000

This means you've spent more than the value of work completed (EV) but less than what was planned (PV).

Calculating EV, PV, and AC

To effectively use EVM, project managers must understand how to calculate these key metrics:

  • PV = BAC * % of planned completion (where BAC is the Budget at Completion)
  • EV = BAC * % of actual completion
  • AC = Sum of all costs incurred for the work completed

Comprehensive Example:

Let's consider a construction project with the following details:

  • Total Budget (BAC): $500,000
  • Project Duration: 12 months
  • Current Time: 4 months into the project
  • Planned Completion: 35%
  • Actual Completion: 30%
  • Actual Costs Incurred: $160,000

Calculations:

PV = $500,000 * 35% = $175,000

EV = $500,000 * 30% = $150,000

AC = $160,000

Practical Tip: Regularly update your project's Work Breakdown Structure (WBS) and track progress at the work package level to ensure accurate calculations of EV, PV, and AC. Use project management software to automate these calculations and generate real-time reports.

Leveraging EV, PV, and AC for Project Control

These metrics form the foundation for several key performance indicators in EVM:

  • Schedule Variance (SV) = EV - PV: Indicates whether the project is ahead or behind schedule
  • Cost Variance (CV) = EV - AC: Shows whether the project is under or over budget
  • Schedule Performance Index (SPI) = EV / PV: Measures schedule efficiency
  • Cost Performance Index (CPI) = EV / AC: Measures cost efficiency

Calculating Performance Indicators:

Using our construction project example:

SV = $150,000 - $175,000 = -$25,000 (behind schedule)

CV = $150,000 - $160,000 = -$10,000 (over budget)

SPI = $150,000 / $175,000 = 0.86 (performing at 86% of the planned schedule)

CPI = $150,000 / $160,000 = 0.94 (getting $0.94 of value for every $1 spent)

Interpreting EVM Metrics

Schedule Variance (SV) and Schedule Performance Index (SPI)

  • SV > 0 or SPI > 1: Project is ahead of schedule
  • SV = 0 or SPI = 1: Project is on schedule
  • SV < 0 or SPI < 1: Project is behind schedule

Cost Variance (CV) and Cost Performance Index (CPI)

  • CV > 0 or CPI > 1: Project is under budget
  • CV = 0 or CPI = 1: Project is on budget
  • CV < 0 or CPI < 1: Project is over budget

Interpretation Example:

For our construction project:

SV = -$25,000 and SPI = 0.86: The project is behind schedule. It has completed 86% of the work it should have by this point.

CV = -$10,000 and CPI = 0.94: The project is over budget. For every dollar spent, we're getting 94 cents of value.

Forecasting with EVM

EVM also allows for project forecasting:

  • Estimate at Completion (EAC) = BAC / CPI: Projected total cost of the project
  • Estimate to Complete (ETC) = EAC - AC: Projected additional cost needed to complete the project
  • Variance at Completion (VAC) = BAC - EAC: Projected over/under budget at completion

Forecasting Example:

For our construction project:

EAC = $500,000 / 0.94 = $531,915

ETC = $531,915 - $160,000 = $371,915

VAC = $500,000 - $531,915 = -$31,915

Interpretation: If the current trend continues, the project is forecasted to be completed at $531,915, which is $31,915 over budget. An additional $371,915 is needed to complete the project from this point.

Benefits of Using EVM

  • Early detection of performance issues
  • Improved project forecasting
  • Enhanced stakeholder communication
  • Better decision-making based on objective data
  • Increased project control and risk management

Implementing EVM in Your Projects

To successfully implement EVM:

  1. Develop a detailed project schedule and budget
  2. Break down the project into manageable work packages
  3. Establish a baseline for measurement
  4. Regularly collect and analyze EV, PV, and AC data
  5. Use EVM metrics to inform project decisions and corrective actions
Exam Tip: For certification exams, be prepared to calculate EV, PV, and AC given various project scenarios. Practice interpreting these values and their derived metrics (SV, CV, SPI, CPI) to assess project health. Also, understand how to use these metrics for forecasting (EAC, ETC, VAC).

Conclusion

Earned Value Management, with its core components of Earned Value, Planned Value, and Actual Cost, provides project managers with a powerful toolkit for monitoring and controlling project performance. By mastering these concepts and implementing EVM in your projects, you can significantly enhance your ability to deliver successful outcomes and drive continuous improvement in your project management practices.

Remember, while EVM provides valuable insights, it should be used in conjunction with other project management techniques and always interpreted within the context of your specific project and industry.

Become a Certified Project Management Professional (PMP)®

Gagan Singh

I am an experienced Project Manager and Security Professional with a proven track record of delivering complex, multi-million-pound Critical National Infrastructure (CNI) projects in the public sector. My expertise lies in leading large, diverse teams and fostering collaboration across intricate stakeholder landscapes to drive successful project outcomes. I combine strong technical skills with a strategic mindset, ensuring that innovation and organizational goals align seamlessly.

With industry certifications including PMP®️, CISSP®️, CCSP®️, and CompTIA Security+, I bring a deep commitment to excellence in project management and cybersecurity. As a PMI Authorized PMP®️ Instructor, I offer Project Management Practitioner PMP Training through LIVE instructor-led classes. This allows me to share my extensive knowledge and experience directly with aspiring project managers in an interactive, real-time environment.

I am passionate about sharing knowledge, mentoring future project managers, and supporting the development of talent in the field. My hands-on approach to training, combined with my practical experience in delivering critical infrastructure projects, provides a unique and valuable learning experience for those seeking to advance their project management skills.

https://www.projectmanagementpathways.com/
Previous
Previous

Leveraging the Salience Model: Revolutionizing Stakeholder Management in Projects

Next
Next

SPI and CPI: Essential Project Performance Metrics Explained