Cost baseline

The approved, time phased budget a project is measured against, made up of the priced work packages plus their contingency reserve, and excluding management reserve.

The cost baseline is the number a project is held to, not the number the organisation has set aside. Priced work packages plus contingency reserve make the baseline; adding management reserve on top gives the total budget, which is why the two figures rarely match and why quoting the wrong one starts an argument. Every cost variance and every performance index is calculated against the baseline, so changing it resets the record of how the project has performed so far. That is the reason a baseline change is a governance act with a name attached rather than a spreadsheet edit.